MME80001 | Resource Planning Management 3 | Accounts

A machine foundation is planned to cost $100000. At one stage observation of this foundation work, the actual cost of work performed was $35000. The planned value and the earned value at that stage were worth $45000 and $40000 respectively. The cost variance at this stage is: a.